This weekends progress was as follows:
Removing all the rubbish into the skip
Removing the timber cladding and shutters on the front elevation
Isolating all the electrics and removing old wiring
Cutting all chases and breaking out about 70%
All necessary floors lifted
Removed secondary double glazing and frames
Removed sliding door between lounge and dining room.
During this week:
Installed loft ladder
Stripped kitchen wallpaper
Sized and selected radiators
Designed kitchen layout
Ordered double glazing.
Thanks to Dave, Dan and Matt for clearing the rubbish on Saturday. Big thanks to Matt for chasing out all day today.
Pictures at: http://photosbytony.fotopic.net/